Installation of Vacuum Tower for Khabarovsk Oil Refinery Plant (NPZ)

Installation of Vacuum Tower for Khabarovsk Oil  Refinery Plant (NPZ)


   Installation of  oil&gaz equipment with total 240 tns, and 35 m length , 8,5 m diameter was fulfilled on 22 December 2011.
To implement the terms of contract  two heavy duty cranes were delivered to Khabarovsk. Installation operations were made in two stages: installation in vertical position and revolving along the axis to 160 degrees. It took two days to make it over the operations taking into account that the weather conditions were very severe with the temperature -26 C .
Just remind you that in accordance with the terms of contract the Company SWTrans undertook commitments for unloading of  vessel, road carriage and installation of vacuum tower as it had been reported earlier in the article “SWTrans at Far East!” on 28.11.11

 Монтаж вакуумной колонны 240 тонн

 

Монтажные работы по подъему колонны весом 240 тонн

 

Монтаж и установка вакуумной колонны

 

 Установка вакуумной колонны на строительно-монтажной площадке


производство монтажных работ по установке колонны 240 тонн

 